132/11 KV Sub-station for M/s DEWA @ MAKHAZEN, JAFZA, Dubai

PROJECTS

132/11 KV Sub-station for M/s DEWA @ MAKHAZEN, JAFZA, Dubai

INFRASTRUCTURE

PROJECT INFO:

Client: Dubai Electricity & Water Authority.
Consultant: Lakshmi Engineers Architects & Designers (LEAD).
Main Contractor: KEC International Limited, Abu Dhabi.
Location: Makhazen, JAFZA, Dubai.

PROJECT DESCRIPTION:

Construction, supply, installation, testing & commissioning of MAKHAZEN 132/11 KV Substation and associated works – civil, finishing, metal, plumbing and drainage work done for the basement, ground & first floor. Equipping transformer, capacitor bank & earthing the transformer rooms. Fire pump room, security room and fire water tank foundations. Also, external work consisting of stormwater manholes, soakaway, oil-water tank, interlocks and compound wall, including gates.